Skip to the main content
CONTRACT AWARDUpdated 2 months ago

Construction of Kankan 225/30 kV Substation, PIEGM

Engineering, supply and construction of the Kankan 225/30 kV substation under the Guinea-Mali Electricity Interconnection Project (PIEGM), financed by IDA credits 62610 and D3360.

English, French, Portuguese or Arabic, machine translated, with the original kept beside it.
Key Information
Awarded by
Electricite de Guinee (EDG)
Location
Upper Guinea, Kankan Region, Guinea
Status
Awarded
Category
Works
Award Amount
USD 13,167,065
Size
mega
Reference
P166042-WORKS-SUBSTATION-KANKAN
Language
English
Contract End
Feb 28, 2025

Overview

Works contract under the Guinea-Mali Interconnection Project (P166042). Scope covers design, supply and installation of high-voltage equipment including a 225/30 kV transformer, switchgear, control and protection systems, and commissioning of the Kankan substation. Initial contract value USD 9,358,505.21, with a price adjustment of USD 3,808,560.16 representing 40.69 percent of the initial contract. As of 30 September 2024 the overall physical progress was 69.55 percent. The previous implementation mission noted slow progress due to inadequate mobilization of material and human resources by the contractor. Since that mission, the contractor deployed additional staff and machinery on site, allowing the progress rate to reach 69 percent. The main electrical equipment including the transformer was shipped and expected for delivery in Conakry by 30 November 2024. Completion of works is scheduled for 28 February 2025. Contractor name not disclosed in the public Implementation Status Report.

Scope of Work

Design, supply and installation of 225/30 kV transformer and high-voltage switchgear, control and protection systems, civil works, commissioning, and operator training for the Kankan substation.

Selection Criteria

Contractor identity not named in the public Implementation Status Report. Initial contract value USD 9,358,505.21 with a subsequent price adjustment of USD 3,808,560.16 (+40.69 percent). Project is financed by IDA credits 62610 and D3360 under the Guinea-Mali Interconnection Project P166042.